"Harnessing Smart Irrigation and Solar Power for Increasing Employment in Cihanbeyli"
Ahi Y. (Yürütücü), Gültaş H. T., Dündar M. İ., Akbulut V.
AB Destekli Diğer Projeler, 2025 - 2026
- Proje Türü: AB Destekli Diğer Projeler
- Başlama Tarihi: Temmuz 2025
- Bitiş Tarihi: Eylül 2026
Proje Özeti
1.1.
Executive
summary of the Action
The
main objective of the Action is to create sustainable employment opportunities
for SuTPs and LHC members through productivity growth driven by the
installation of solar-powered smart irrigation systems in Cihanbeyli. During the
reporting period, the Action progressed successfully, achieving all major
technical and operational milestones.
Within
the scope of Activity 4, the Project Coordinator and the Secretary were hired
based on their qualifications, and 4 SuTP staff members were also recruited.
Within the scope of Activity 2, the complete smart irrigation infrastructure,
including soil moisture, salinity and temperature monitoring stations, was
installed, and the solar energy system was fully deployed and is now
operational, supporting the irrigation pumps. The digital monitoring platform
was established and integrated with the field sensors under Activity 3,
enabling real-time irrigation management in line with the project’s objectives
on resource efficiency and productivity improvement.
All
planned capacity-building activities were delivered in line with Activities 4
and 5, including theoretical and practical trainings for cooperative members as
well as newly hired SuTP and LHC employees. In total, 112 cooperative members
and all six new staff received technical training on water and energy
efficiency, field operations, and system monitoring. These trainings directly
contributed to performance indicators related to improved technical capacity
and enhanced resource efficiency, while also supporting the cooperative’s
operational growth.
A minor change was implemented during the
period, as officially submitted through a notification to ICMPD, based on the
change proposal submitted in September 2025, involving an internal reallocation
between Budget Lines 3.5.1 and 3.5.2. The number of soil moisture sensors was
revised based on field conditions and seasonal constraints, reducing the total
from 100 to 42, which allowed reallocation of €7,115 to the solar system. The
justification for this reallocation was mainly based on the on-site assessment,
which showed that the irrigation season was close to completion and that
harvesting and soil tillage activities were about to start in several parcels;
therefore, installing all initially planned sensors would not have been
technically efficient and could have required dismantling newly installed
stations. In addition, the revised sensor configuration was considered
sufficient to meet the project’s monitoring and training needs, while the
additional allocation to the solar system was necessary to cover the increased
actual costs and the minimum requirement of 176 panels for full system
functionality. This adjustment did not affect the scope, quality, or
sustainability of the smart irrigation system and enabled the cooperative to
procure the required number of solar panels (176 units) to ensure full system
functionality.
Overall,
the Action was completed on schedule with no major delays. The completion of
all system installations, together with the successful implementation of
extensive training activities and dissemination efforts, strengthened the
cooperative’s institutional and operational capacity and contributed directly
to the achievement of key outputs related to enlarged operational capacity,
enhanced productivity, and sustainable employment creation. Accordingly, the
Action has been finalized in line with its objectives, expected results, and
sustainability perspective.